The Record / Front Street's commercial rebuild

Five permits in July, fourteen in September, and the first building permit on September 22.

Corrected by reporting in August 2026. First business building permit issued September 22, 2026. Updated November 16, 2026.

What was said

Overall, five commercial permits have been issued for Lahaina town (one is under construction).

Maui County news release · July 1, 2026 · County of Maui

Of the 36 remaining (mauka) properties, 14, over a third, are actively moving through planning and permitting.

County of Maui, Three-Year Recovery Milestone Report · August 7, 2026 · Maui Now

Six have received planning permits (some also with building permits in review), five are in plan review and three are in preapplication consultation.

County of Maui, Three-Year Recovery Milestone Report · August 7, 2026 · Maui Now

Of those 36, 14 have permits at some stage. Some of them have already received their historical district permit, which means they can rebuild in this historic district.

Mayor Richard Bissen, PBS Hawaiʻi debate · September 3, 2026 · PBS Hawaiʻi, at 39:34

What happened

Where it stands as of October 26, 2026

  • One building permit to rebuild a Front Street business, issued September 22, 2026, for 612 Front Street, where construction began October 12.
  • The county says two building permits have been issued for the 36 mauka Front Street properties; 612 holds two permit numbers, and we found no other issued building permit among the lots we track.
  • In the county’s permit system on October 26: 714 Front Street, filed May 30, 2025, is still “Waiting for Payment,” with grading and roadway permits filed October 13; 744 and 764 Front Street are still in review.
The claims, checked 2 comparisons, with sourcesShow

“Overall, five commercial permits have been issued for Lahaina town (one is under construction).”Maui County news release, July 1, 2026 · County of Maui

Maui Now checked the five addresses a month later: 612, 632, 714, 724 and 764 Front Street. At the July 1 meeting and a July 2 press conference a county deputy managing director had listed them as having “received a permit”; what they had received was historic-district approval, with shoreline and flood sign-offs where needed. Those come before a building permit, not instead of one. The manager of 612 Front Street said he was getting calls after a county official said the property already had a building permit: “This is not the case yet.” The paper’s finding: “Not one recovery building permit has been issued for a commercial property destroyed on Front Street.” We checked the county’s permit system on September 17: no rebuild building permit at any of the five, and three applications in review, the oldest filed May 30, 2025.

Maui Now, Aug. 2, 2026, Maui County permit system, 612 Front St.

“Of the 36 remaining (mauka) properties, 14, over a third, are actively moving through planning and permitting.”County of Maui, three-year report, August 7, 2026 · Maui Now

“Of those 36, 14 have permits at some stage.”Mayor Richard Bissen, PBS Hawaiʻi debate, September 3, 2026 · PBS Hawaiʻi, at 39:34

The county’s own report breaks the 14 down: six with a planning permit, five in plan review, three in pre-application consultation. A planning permit is the historic-district approval; it does not allow construction. A building permit does. When the mayor spoke on September 3, no building permit had been issued to rebuild a destroyed business anywhere on Front Street. We checked every permit of every type on the street on September 20. The first came on September 22, 2026, for 612 Front Street, the former six-tenant retail building: permits B2025-02062 and B2025-02063, applied for December 23, 2025. Three years and six weeks after the fire. At the end of September, 714, 744 and 764 Front Street were still in review. Construction at 612 Front Street began with a blessing on October 12, 2026; the owner expects about six months of work and an opening in summer 2027. On October 21, in the county’s announcement of the ʻUlu o Lele marketplace, Maui Now reported the county’s tally for the 36 mauka Front Street properties as two building permits issued, four applications under review and 16 properties “on a pathway to rebuilding.”

Maui Now, Aug. 7, 2026, PBS Hawaiʻi, Sept. 3, 2026, Maui County permit system, permit B2025-02062, Maui Now, Oct. 13, 2026, Maui Now, Oct. 21, 2026

Questions still open 3 questionsShow
  1. Which five approvals did the county count as “commercial permits” on July 1, and which building was under construction?
  2. What stage is each of the 14 lots at today, and how many hold a building permit?
  3. What is each application in county review waiting on, and since when?