03 · Front Street Five permits in July, fourteen in September, and the first building permit on September 22.
On July 1, 2026, the county announced that five commercial permits had been issued for Lahaina town and that one building was under construction. A month later a reporter checked the five addresses. The approvals were historic-district and shoreline sign-offs, the steps that come before a building permit, and none of the five had a building permit. In September the mayor said 14 of the 36 buildable Front Street lots had permits “at some stage.” The county’s own report puts those 14 at six planning permits, five in plan review and three in early consultation. The first building permit to rebuild a business on Front Street was issued on September 22, 2026, three years and six weeks after the fire. Three more are pending: one is marked “Waiting for Payment” in the county’s permit system, and two are still in review.
Corrected Corrected by reporting in August 2026. First business building permit issued September 22, 2026.